Whats Happening ?

Friday July 16th

Norman helps Adrian to dry-lay 2 coping ‘stones’ and they then begin dismantling a section of scaffold finished with revealing the newly topped length of wharf wall.  It looks really good!

Alistair and Viv’ arrive for the weekend.

Monday July 12th

Adrian casts another 4 coping ‘stones’

Saturday July 10th

Adrian presents an illustrated talk on the Rolle Canal at South Molton Assembly Hall

Thursday July 8th

Trevor and Adrian give the 360°excavator and dumper truck some attention checking oil levels, refuelling and greasing all the relevant parts.

They then set 3 coping ‘stones’ in place on the wharf wall.

Wednesday July 7th

Trevor and Adrian remove the mould from the coping ‘stone cast the day before.  They then distress the face and top surface before reassembling the mould and casting another block.  Following this they spend time digging silt from the pile and using it to level parts of the site.