Whats Happening ?

Wednesday August 4th

Adrian and Trevor finish laying all the cast blocks in place and once they are all levelled they are mortared in and backed up with concrete.

Tuesday August 3rd

Trevor and Adrian begin moving the earlier cast blocks into position on the wharf wall and levelling them up.

Monday August 2nd

Another repeat of the block-making performance brings the total number produced so far to 75 including the quoin ‘stones’.

Sunday August 1st

Adrian repeats the performance with casting blocks.

Saturday July 31st

Adrian removes the shuttering from the block cast the day before, re-assembles it and then casts another.  He next collects his trailer with all the sawn timber on and takes it down to Sea Lock.